Nov 042017
 

Summary
The proponent has received the last approval from the provincial government needed for their proposed construction. However this was based on inadequate environmental work done by the proponent. Furthermore, the proponent’s plan to use used overseas shipping containers instead of actual settling tanks risks contaminating the Precambrian Shield parking lot, the District Municipality of Muskoka’s land to the west of it, and the Moon River with insecticides and other unknown chemicals.
 

Detail
The proponent for the proposed hydro-electric generating station at the Bala falls needs two main areas of excavation, as shown below (click on all  images for a larger view):

  1. The proposed intake would be between the District’s highway bridge and the MNRF’s Bala north dam. This proposed excavation requires a cofferdam with removable panels, so that the cofferdam could be removed within 24 hours if required to avoid flooding from a rain storm during this proposed work. The proponent hopes to start this excavation within the next week or so.
  2. The excavation for the proposed station would be started in a few months.

Due to rain, leaks through the proposed cofferdam, and ground water, the proponent would need to pump water from these proposed excavations. This water would likely have sediment and other materials which should not be pumped into the Moon River, so the proponent requires an approval to do this, and some of the required steps are as follows:

  1. The proponent prepares a plan detailing the proposed; work, locations, construction sequence, equipment, precautions and submits this application to the Ministry of the Environment and Climate Change (MOECC).
  2. Due to the MOECC’s Statement of Environmental Values the MOECC has an obligation that their decision-making is open. So the MOECC are to post a Proposal of these plans on their Environmental Registry web site and provide the opportunity for the public to provide comments. As provided by the Environmental Bill of Rights (EBR, more here), the public has the right to appeal any subsequent approvals to the Environmental Review Tribunal.
  3. Once the MOECC decides they have considered the environmental impacts of the proponent’s plans and the comments received from the public, the MOECC can issue an Environmental Compliance Approval (ECA, which is referred to as an “Instrument”) for the proposed works.

On May 30, 2016 the MOECC did post a Proposal for this ECA, with a 45-day public comment period, and on June 30, 2016 SaveTheBalaFalls.com did provide comment. However, sometime in the following two weeks the MOECC determined that: “The instrument proposal notice for the ECA was originally posted accidently on the Environmental Registry. The ECA application is exempt from posting as it was subject to requirements under the Environmental Assessment Act.” This exemption is due to Section 30 of the EBR and a main reason the MOECC claims it is to remove the right of appeal.

As posted here, on October 20, 2017 the MOECC did issue this last approval the proponent needs from the provincial government for the construction of their proposed project, and indeed it does claim: “As the decision to issue this Environmental Compliance Approval exempt from requiring an EBR posting, Leave to Appeal rights do not apply.” However, there are restrictions to this exemption, for example, that: “the environmentally significant aspects of a proposal … have already been considered in a process of public participation”. As shown below, the public has certainly not been informed of major environmental issues, nor has there been any “process of public participation” – that is, these issues were not disclosed to the public as part of the the environmental assessment process, which ended in 2013. 

A main requirement for dealing with water pumped from an excavation is the settling tank, in which water slowly passes through, allowing sediments to settle to the bottom, the water can be retained and tested, and when clean and clear enough, the water is pumped into a storm sewer or to the nearest water body, which would be the Bala south channel and the Moon River for the proposed project.

The proponent’s ECA application included some pages from the Aquatech Dewatering Company, and indeed the issued ECA approval stated that the settling tanks are to be: “Aquatech Models or approved equivalent”. The photograph below shows a typical Aquatech settling tank.

The picture below shows a typical settling tank from the Atlas Dewatering Corporation.

Instead of the above commercial settling tanks, the proponent currently has six used overseas shipping containers at the north end of the Precambrian Shield parking lot, which they intend to use as settling tanks.

We frequently hear of invasive species such as the Asian long-horned beetle and Emerald Ash Borer infesting our trees, and one concern is that these could arrive inside overseas shipping containers. To prevent this, receiving countries require the shipping container manufacturers to treat the wood floors of their shipping containers with insecticides.

The photograph above is of the metal data plate riveted to one of the shipping containers currently in the Precambrian Shield parking lot. It states that the wood floor was treated with the chemical Radaleum-FHP-60.

Another one of the shipping containers currently in the Precambrian Shield parking lot states that the wood floor was treated with the chemical Talileum 300.

The active ingredient of these chemicals is Cypermethrin, which is a broad-spectrum insecticide known to be harmful to fish. While these shipping containers are old, it is not known how much of these chemicals remain, as they have likely never been washed out. Also unknown is what materials these shipping containers have been used to transport, and what harm these could cause if washed into the Moon River.

There is also some unknown black material coating the floor of these shipping containers.

As shown above, the proponent has cut holes near the top of the wall of their shipping containers, so that a section of 12″-diameter pipe will enable water to pass from one shipping container to the next.

The problem is that the pipe is rusty and no matter how much caulking is used, there will be leaks.

These shipping containers are directly adjacent to each other, arranged in a 2×3 grid, so it would not be possible to see or contain the leaks.

Similar to the back of a transport truck trailer, the end of each shipping container is a double door. While there is a gasket seal, the purpose of this is to keep water splashes out. And being more than ten years old, these rubber gaskets are deteriorating, so would not create a water-tight seal against the rusty metal. These doors would leak.

This leaking water would contaminate the Precambrian Shield parking lot, and as the ground is sloped towards Muskoka Road 169, where there is a drainage ditch leading to the Bala south channel, this would also contaminate the District Municipality of Muskoka’s land. In fact, these shipping containers are too close to Muskoka Road 169 and are partially on the District Municipality of Muskoka’s road allowance even though the proponent doesn’t have permission for this.

We have requested that the proponent not be allowed to use these shipping containers, and that they be immediately removed from the Precambrian Shield parking lot.

Nov 042017
 

Summary
As we have noted for several years (for example, in the article here), the proponent’s environmental investigations have been entirely inadequate, with the result that their work could result in releasing toxic waste such as PCBs into the Moon River, causing irreparable environmental harm. We have therefore submitted the following:

  • A request to the Environmental Commissioner of Ontario that the MOECC review the last approval issued to the proponent as it would not protect the environment or public.
  • A request to the Environmental Review Tribunal to revoke the last approval issued to the proponent, as this approval was based on inadequate environmental testing by the proponent.
     

Detail
The Bala #2 Generating Station was built in 1924, and is shown in historical official surveys, such as the March 29, 1924 drawing below (click on it for a larger view), which is entitled: “Plan of Part of the Town of Bala, District of Muskoka, Shewing Proposed Power Development”. The building itself is shown as “Proposed”, and having dimensions of 16′ x 16′.

The survey below was done a few months later, in August 30, 1924, likely because not only has the Bala #2 Generating Station been built (it is no longer referred to as “Proposed”), but the land has been transferred to the Bala Electric Light & Power Company.

A few years later, in 1929, a portion of the land was sold to the Hydro-Electric Power Commission of Ontario, which was how the province came to own the currently-proposed construction site.

That is, it is well-established exactly where the Bala #2 Generating station was located.

The Bala #2 Generating Station operated until 1957, a colour photograph of it is here (this photograph would have been taken before 1954, as that is when the current bridge over the Bala north channel was built). During these 33 years of operation, the machinery (and floor) would have accumulated significant grease and oil.

After being idle for 15 years, in 1972, the Bala #2 Generating Station was demolished. There seems to be no record of what happened to the hazardous materials, whether they were removed or buried. But what is known is:

  • From 1929 to 1979 polychlorinated biphenyls (PCBs) were widely used in electrical equipment, such as the “step-up” electrical transformer the Bala #2 Generating Station would have needed.
  • PCBs were found to be toxic.
  • When the Bala #2 Generating Station was demolished, PCBs were still legal and being used, and there were very few environmental requirements for demolitions.
  • When demolishing something that has a pit at the bottom, it is certainly easier and less expensive to leave as much at the bottom that fits, than to hoist it out and figure out where else to dispose of it. 
  • There may be a rusty and fragile electrical transformer containing PCBs, and old machinery and floor coated with oils and greases buried where the proponent plans on excavating. This proposed excavation, and driving heavy construction vehicles over this area could cause these hazardous substances to be washed into the Moon River, and to contaminate adjacent soil.

In 2013 the proponent completed a Phase II Environmental Site Assessment (ESA) which is supposed to determine the location and concentration of any contaminants. This ESA work included their drilling three exploratory boreholes at the location shown below. The ESA also determined that the ground water flow is to the west, as shown by the green arrow below.

The black lines in the graphic below are from a recent drawing from the proponent, and the red lines are from the above historical survey, rotated and scaled to match the recent drawing as close as possible. 

Two important observations are:

  • The only test result which exceeded the Ministry of the Environment and Climate Change’s (MOECC’s) guidelines was for Zinc in ground water, and this was from the borehole closest to the likely source of contamination – the site of the Bala #2 Generating Station.
  • All three of the boreholes were drilled upstream of the site of the Bala #2 Generating Station.

It is therefore possible that:

  • The ground water is far more contaminated that reported, as the contamination would flow downstream away from the boreholes.
  • There are PCBs, oils and greases that would be dispersed into the Moon River as a result of the proponent’s planned excavation.

The proponent’s proposed construction site must be treated as the abandoned industrial facility that it is, and there are required steps to protect the environment and public. The proponent must be required to follow these.

We have therefore requested that the proponent be required to stop work until they can show that harmful substances would not be released into the Moon River.

Nov 042017
 

AM640 radio host Kelly Cutrara visited Bala during the Cranberry Festival and was so disappointed by the destruction being caused by the proposed project, that the next day we were invited for an interview, which was from 3:45 to 4:00 pm on Monday October 16, 2017.

You can listen to it here …

Oct 132017
 

Incorrect information from the proponent
As detailed in our article here, the proponent has long been providing misinformation to the public, and more recently they are also providing misinformation to the Ministry of the Environment and Climate Change, as part of an application for approval.

But now the proponent is providing misinformation in fanciful renderings with which they are attempting to mislead the public. For this Bala Cranberry Festival weekend, the proponent has defaced Bala with graphics that are; wrong in what they show, and are wrong in what they neglect to show. Detail is provided in our article here(click on each image for a larger view).

And on this topic, we note that in the nine years that the SaveTheBalaFalls.com web site has been providing the community with information on the proposed project to build a hydro-electric generating station at the Bala falls, and for the hundreds of articles posted on it (you can review articles older than those listed under “Recent Articles” using the “Articles by month” pull-down at the very bottom-right at SaveTheBalaFalls.com), the proponent has never contacted us to inform us of any errors on our web site, nor have they refuted any of the information on our web site.
 

No answers or responses from the proponent
In their written replies to us, the MOECC and the Ministry of Natural Resources and Forestry often suggest we contact the proponent, or that we should refer to the proponent’s web site, for answers.

Over the past two years we have written 11 polite and respectful letters asking the proponent questions, but they do not respond.

We also check the proponent’s web site regularly, and there is no useful information on that either. The proponent does not post their recent approvals, their posted drawings are out-of-date, and their renderings are incorrect.

In summary, the proponent only provides misinformation to the public.
 

Current status
The proponent has received some approvals for the pre-construction work to build a proposed hydro-electric generating station at the Bala falls – for example, their current mess and destruction is to build an upstream cofferdam between the highway bridge and Bala north dam.

But the proponent still needs approvals to begin the construction work. That is an odd decision they’ve made to start work before they have all the approvals they need to actually do the work.

Our main concern is that it would be unprecedented to build a hydro-electric generating station in the middle of a very popular in-water recreational area, yet the government and proponent refuse to disclose a safety plan to show how, or if, the proposed project could be operated safely.

Our assessment is that the proponent has made so many changes to their plans that received environmental approval in 2013, that they would be building a different – and too dangerous – project. We therefore continue to ask the government to inform the proponent that if they wish to proceed with their current plans, the proponent be required to submit an Addendum for their environmental assessment.

In several other places in Ontario, projects with much more work done than here have been cancelled, and if the proponent can’t show they could do this safely, then we’re asking that this proposed project be cancelled. And we’ll keep at it, as we have for the past 12 years.
 

Proponent’s Construction Meeting
On Thursday September 21, 2017 the proponent hosted a public meeting (only their fourth in the more than 12 years it has been pursuing this opportunity) at the Bala community centre.

An article concerning the incorrect and uninformed statements they made at the meeting is posted here.
 

Recent happenings
An article with video from the proponent’s Construction Meeting and other recent media and political updates is here.

In addition, well-known energy expert Tom Adams has posted a Guest Post from SaveTheBalaFalls.com. That post notes the correlation that highly controversial proposed energy projects are cancelled in ridings held by Liberals, but are approved by the MOECC in ridings held by the Progressive Conservative Party of Ontario. More detail is in the article here.

Oct 122017
 

The proponent has recently provided some new renderings, here marked-up with call-outs to highlight some of the false information, deceit, deception, untruths – let’s be blunt – lies (click on any image for a larger view).

The rendering above seems to be a delightful scene, except it is all a lie. There would only be a trickle down both falls, but the water from the proposed generating station would be dangerous for the guy in the canoe. And they have neglected to show their inadequate proposed downstream safety boom, and the huge steel gates on both the intake and at the tailrace of the proposed generating station.
 

Here’s the view of the proposed generating station from the street. For their original proposal, and for the environmental assessment for both their original Option 2 design, and for their subsequent Alternative 1A design the proponent committed this would be below street level. Instead it would tower more than 2½ storeys above street level, blocking the view down the Moon River. Instead of people on the bridge enjoying the view of the Bala north falls, they would see the dry rocks where the falls used to be, while listening to the roar of the ventilation fans for the proposed generating station.
 

The proponent would build a portage, which would encourage people to canoe through the water –outside of the proposed downstream safety boom – which would be made dangerous by their proposed generating station.
 

The proponent committed they would leave untouched the south end of Portage Landing, which they are leasing from the Township of Muskoka Lakes. Instead, they cut down all the trees adjacent to Muskoka Road 169, down to where the bridge starts.

Oct 092017
 

It has been clear for too long that Ontario’s environmental assessment process is a farce. For example:

  • The MOECC accepted the proponent’s Environmental Impact Study, which claimed a net benefit, even though it didn’t even try to assess the negative impacts.
  • For their environmental assessment, the proponent made many commitments that their proposed generating station would not rise above road level, it would not have a larger footprint, and it would not impact heritage landscapes. They will not honour any of these.
  • For their proposal, the proponent made commitments such as they would not impact in-water recreation. They would not honour these either.

But now we know what kind of farce it is – a political farce. Look at the status of the following seven controversial proposed electricity generation projects:

  • The first three, in ridings held by Liberals were cancelled.
  • The next four, all in ridings held by the Progressive Conservative Party of Ontario, have been approved by the Ontario Liberal government.
Proposed project Local MPP at the time Status
Oakville gas-fired generating station Liberal, Kevin Flynn, Oakville Cancelled by Ontario Liberal government.
Mississauga gas-fired generating station Liberal, Charles Sousa, Mississauga South Cancelled by Ontario Liberal government as part of an election promise.
Thunder Bay wind turbines (Big Thunder wind project) Liberal, Bill Mauro, Thunder Bay-Atikokan Cancelled by MOECC.
South River hydro-electric generating station PC, Norm Miller, Parry Sound-Muskoka Approved by MOECC, currently in operation.
Almonte hydro-electric generating station PC, Jack MacLaren, Carleton-Mississippi Mills Approved by MOECC, currently under construction.
Collingwood wind turbines (Fairview wind project) PC, Jim Wilson, Simcoe-Grey Approved by MOECC, but cancelled after six teams of lawyers and more than $1,800,000 of legal fees for appeal to the Environmental Review Tribunal, that agreed the eight 45-storey-tall wind turbines too close to two airports would be a danger to human life – which the MOECC had refused to accept.
Bala hydro-electric generating station PC, Norm Miller, Parry Sound-Muskoka Environmental Assessment approved by MOECC, who have stated they expect to issue the required Environmental Compliance Approval “in the near future”.

 
Clearly, there are political forces here which are subverting the MOECC from fulfilling its mandate.

Oct 062017
 

Some recent events and articles …

  1. On September 21, 2017 the proponent hosted a “Construction Meeting” in the Bala Community Centre, which was their fourth public meeting, in the more than 12 years they’ve been pursuing this opportunity. Huntsville’s YourTV covered the event, and their reporting is here.
     
  2. YourTV posted additional coverage of the proponent’s Construction Meeting here.
     
  3. The proponent made many incorrect and misleading statements during their Construction Meeeting, a letter detailing some of these is posted in the article here.
     
  4. September 25, 2017, Question Period: During the Ontario Legislature’s Question Period on September 25, 2017, our MPP Norm Miller asks the Minister of MNRF for the public safety plan on how the proposed hydro-electric generating station at the Bala falls could be operated safely. She refuses to provide it. The video is here.
     
  5. Septmber 28, 2017, Question Period: On September 28, 2017 MPP Miller asks again for the public safety plan, and the Minister again refuses to provide it, as you can see here. A public safety plan which both the proponent and government refuses to disclose to the public, that sounds very bad. What are they hiding.
     
  6. In response to a Letter to the Editor (on-line here, archived copy here), on October 5, 2017 MuskokaRegion.com published our response (on-line here, archived copy here).
     
  7. At the proponent’s Construction Meeting, they stated people are not “supposed to be” in the Moon River. This is not true, which my dictionary says is therefore a lie. We’ve posted more detail here
Oct 062017
 

In the past, we have documented how the proponent has lied to the public, click on each of these for examples:

Now the proponent is providing incorrect information to the Ministry of the Environment and Climate Change as well. My dictionary defines a lie as: “A statement that deviates from or perverts the truth”. The proponent is providing incorrect information in their application to the MOECC for approval for the settling tanks needed for the construction of their proposed hydro-electric generating station at the Bala falls. As detailed in this letter, the proponent has:

  • Stated they could locate settling tanks in the Portage Landing / Don’s Bakery parking lot, but they could not.
  • Stated the type of cofferdam they would install, but they would install a different type. This is significant as it affects the quantity and capacity of settling tanks required, so these may be inadequate.
  • Not informed the MOECC that the MNRF requires that this cofferdam be removable on 24 hours notice.
  • Somehow indicated to the MOECC that the nearest residence is almost a kilometre away, when in fact there are residences within 70 m of the proposed construction site.
  • Not informed the MOECC, or the public, that they would install a tower crane above the Moon River, and this could drip lubricating oil and other deleterious substances directly into the Moon River. Such negative impacts, and their mitigation, are to be disclosed as part of an environmental assessment, but were not.

Remarkably, the MOECC has replied that they can make decisions based on incorrect information received from the proponent. This is not right. We again request that the MOECC require the proponent to provide the correct information, as part of an Addendum to their environmental assessment.

Oct 062017
 

At the proponent’s Construction Meeting at the Bala Community Centre on September 21, 2017, in response to the unaddressed dangers the proposed project would create for in-water recreation, Moderator John Kim Bell replied: “they weren’t supposed to be swimming in there”.

This is incorrect.

The Moon River is a navigable waterway, and therefore the public has every right to “go jump in the lake” (or river) if they wish, as is provided by the common law riparian right of access.

We well know that the Ministry of Natural Resources and Forestry has a sign posted on the Bala north dam which warns: “Danger, Fast Water, Keep Away”. This sign pertains to the dangers created by the Bala north dam at the top of the Bala north falls, and indeed people should be mindful of the water over these falls.

But our concern is the dangers the proposed hydro-electric generating station would create far from the influence of the Bala north dam. As shown in the figure below (click on it for a larger view), the concern is that the proposed project would make the water dangerous:

  • In the middle of the Moon River, and far outside of the proposed downstream safety boom.
  • In front of people’s private docks.
  • For people travelling to and from the municipal docks on the Moon River, which are the only public docks on the Moon River. For example, as shown in this article.

The MNRF’s warning sign does not apply to the entire Moon River. And the doctrine of reasonable use precludes the proponent from depriving the public from use of the Moon River.

The public has the right to swim in the Moon River, so it is a lie to say: “they weren’t supposed to be swimming in there”.

Sep 262017
 

On Thursday September 21, 2017 the proponent hosted a public meeting (only their fourth in the more than 12 years it has been pursuing this opportunity) at the Bala community centre.

As a result of their making many incorrect and ridiculous statements, they were interrupted several times (you can view some of the meeting here). As a result, they terminated the meeting early.

One of the proponent’s incorrect statements claimed they have environmental approval for the roof of their proposed building to be above Muskoka Road 169, and therefore blocking the view down the Moon River with an ugly concrete building.

To correct these and other incorrect statements by the proponent, SaveTheBalaFalls.com sent this letter.